Fiber-to-the-Home Project Updates
- CRMU will post frequent updates with pictures to our project status below:
March 15, 2017
Informational postcard sent to customers!
![](images/postcard.jpg)
February 13, 2017
The first fiber-optic reels arrive.
![](images/FTTH Update Pics/fiber-reels-small.jpg)
February 10, 2017
Materials are starting to stockpile in preparation of spring construction. Two inch duct and pedestals below.
![](images/FTTH Update Pics/duct-and-peds.jpg)
Concrete vaults for fiber below.
![](images/FTTH Update Pics/concrete-vaults.jpg)
---------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------